USU Campus Renovations
Student Events Center
Demolished the USU Barber Shop and built out the new USUSA Student Events Center in the Taggart Student Center, large open gathering and conference room.
Owner: Utah State University
USU FPDC PM : Amanda Thomson
Description:
Date Completed: January 2023
Building: Taggart Student Center
Duration: 3 months
USU Student Financial Remodel
Complete renovation of existing Student Financial Center, including office, glass partitions, millwork, and cubicle.
Owner: Utah State University
USU FPDC PM : Amanda Thomson
Description: Office remodel
Date Completed: November 2022
Building: Taggart Student Center
Duration: 4 months
Engineering Education ReModels
This project involved two locations on campus for the Engineering Education department. It began by demolishing an old distance learning class (ENG 401) and study space (LIB 401). In the engineering building a wall was built, electrical and HVAC re-routed in order to create a mixed use space and a separate conference room. In the Merrill-Cazier Library, we completely stripped and rebuilt the existing space for the Engineering Writing Lab.
Owner: Utah State University
USU FPDC PM : Amanda Thomson
Description: Room full rennovations
Date Completed: October 2023
Building: Anderson Engineering Building, Merrill-Cazier Library
Duration: 3 months
USU CoAL yard storage building
New, ground up pre-engineered metal building, used by USU Facilities for storing materials and equipment.
USU FPDC PM : Loren WIlcox
Description: Pre-fabricated metal building
Date Completed: August 2020
Duration: 3 months
USU Chocolate factory
Renovation of existing retail space, including commercial kitchen, seating area, and retail space.